【导语】以下是⽆忧考整理的历年PMP考试真题及答案,仅供参考。
1.Which of the following is true about accuracy and precision?
A. Precision is consistency and accuracy is correctness
B.Precision is correctness and accuracy is consistency
C.Precision and accuracy are same
D. Precision is used for measuring length and accuracy is used for time measurements Your 下列哪个关于正确度和精确度的说法是正确的?
A.精确度是说连续性;正确度是说是否符合事实
B.精确度是说是否符合事实;正确度是说连续性
C.精确度和正确度是⼀样的
D.精确度⽤来测量长度;正确度⽤来测量你的时间
答案:A 参考:PMBOK2004 CH P154
2.Which process group is associated with schedule control, scope control, and cost control
A. Monitoring and Controlling
B. Planning
C. Executing
D. Closing
哪个过程组包括进度控制,范围控制和成本控制?
A.监控项⽬
B.规划
C.执⾏
D.收尾
答案:A 参考:PMBOK2004 CH P58
3.In Probability and Impact Metrics which of the following statement is true?
A. For opportunities, the high risk (dark grey) zone offers greatest benefits
B. For opportunities, the low risk (medium grey) zone offers lowest risk and best benefits
C. for Risks the high risk (dark grey) zone offers greatest benefits
D. for Risks the low risk (medium grey) zone should be addressed first
关于概率和影响矩阵,下列哪个说法是正确的?
A.对机会⽽⾔,⾼风险(⿊灰⾊)区域意味着代表的利益
B.对机会⽽⾔,低风险(中灰⾊)区域意味着最低的风险和的利益
C.对风险⽽⾔,⾼风险(⿊灰⾊)区域意味着的利益
D.对风险⽽⾔,低风险(中灰⾊)区域应该必须⾸先确定
答案:A 参考:PMBOK2004 CH P210
pmp考试
4.Zero defects practice or Do it first time is associated with which of the following?
A. Crosby
B. Juran
C. Deming
D. Shewhart
零缺陷或者事情⼀次作对和下列哪个有关?
A.克劳斯⽐
B.朱兰
C.戴明
D.休哈特
答案:A
5.Which of the following would be the BEST description of project management plan?
A. It contains risk, cost, process improvement and other management plans.
B. It is one of the outputs of project management software.
C. it is milestone.
D. it is project scope statement.
下列哪个的描述了项⽬管理计划?
A.包括风险、成本、过程改进和其他管理计划
B.是项⽬管理软件的输出之⼀
C.是⾥程碑
D.是项⽬范围说明书
答案:A 解释:⽤排除法,选⼀个相对合适的,注意选项B项⽬管理软件不等于项⽬管理信息系统
6.Purchase order is the simplest example of _________ type of contract
A.T&M Contract
B. Fixed Price
C. Cost plus Incentive Fee
D. Cost plus Fixed Fee
采购单是什么类型合同的例⼦?
A.时间材料合同
B.固定价格
C.成本加奖励费⽤
D.成本加固定费⽤
答案:B 参考:PMBOK2004 CH P230(仔细看能到原⽂)
7.You are the project manager in East West Construction Company. After the completion of the structure you are visiting the site and checking whether the construction is as per the plan by taking the measurements. This is an example of
A. Risk Identification to prevent issues in the future
B. Active project management
C. Quality Assurance activity - Prevention
D. Quality Control Activity - Inspection
你是东西建筑公司的项⽬经理。在完成建筑后,你到实施地点检查是否建筑按照计划进⾏了测量。这是什么的例⼦?
A.风险识别⽤来防⽌未来出现的问题;
B.动态项⽬管理
C.质量保证活动-预防
D.质量控制活动-检查
答案:D 解释:检查作为⼯具出现在两个过程,范围核实和质量控制
8.You are in charge of installing a Voice Response System for a major company. You are about to start preparing the estimates and the Sponsor informed you that the estimate should be as much close to reality as possible. Which of the following you will most likely to use for your estimation:
A.CPM
B.PERT
C.PDM
D. Monte Carlo Simulation
你在负责为某个⼤公司安装声⾳回传系统。你开始准备估算时出资⼈告诉你估算必须尽可能接近实际。你最可能使⽤下列哪个做你的估算?
A.CPM
B.PERT
C.PDM
D.蒙特卡罗模拟
答案:D 解释:蒙特卡罗运⽤统计学进⾏模拟,相对⽽⾔⽐较贴近实际,也可以排除A和C都不是估算,选项B是缺乏经验的时候使⽤的,最没谱。
9.Create WBS is part which Knowledge Area?
A. Project Scope Management
B. Project Time Management
C. Project Integration Management
D. Project Cost Management
创建WBS是哪个知识领域的⼀部分
A.项⽬范围管理
B.项⽬时间管理
C.项⽬整体管理
D.项⽬成本管理
答案:A
10.If the optimistic estimate for an activity is 18 and standard deviation is 3. If the Most likely estimate is 30, the chance the activity will be finished between 23 and 35 days is
A.95.44
B.68.26
C.99.73
D.99.999
如果某个活动的乐观估计是18天,标准差是3。如果最可能估计是30天,这个活动在23天到35天之间完成的概率是?
A.95.44
B.68.26
C.99.73
D.99.999
答案:A 解释:这个活动的最悲观估计 X,(X-18)/6=3;所以最悲观是36;平均估算值=(54+120)/6=29;23到35,刚好左右各两个标准差,概率为95.44%