1. In response to the new regulation about treatment of toxic wastes, you propose a project to make new policies as a PM expert of a toxic waste treatment company.
The proposal reveals the importance of which item below?
A. Taking legal requirements as a basis of initiating projects
B. Looking for mew and effective methods
C. Insisting to behave under legal requirements and ethic standards
D. Time limitation of projects
pmp培训机构哪个好1. 你是一家处理毒废物公司的项目管理专家,为了响应环保机构颁布的有关有毒废物处理的新规定,你建议启动一个项目来编写有毒物质的新处理指南。
这个建议显示了以下哪一点的重要性?
A. 将法律要求作为项目启动的基础
B. 不断寻求新的和有效的方法
C. 坚持按法律要求和道德标准行事
D. 项目必须完成的时间范围
2. This tool and technique of Monitor and Control Risk is applied to examine and document the effectiveness or risk response in dealing with identified risks and their root cause, as well as the effectiveness of the risk management process.
What is it?
A. Risk reassessment
B. Project change requests
C. Project risk audit
D. Workaround
2. 这是一个监控风险的工具方法,它被用以检查并记录风险应对措施在处理已识别风险及其根源方面的有效性。
这是什么工具?
A. 风险再评估
B. 项目变更请求
C. 项目风险审计
D. 权变措施
3. You’re working on an internal service project and are in the beginning of the Planning
processes. You noticed that specific staff members were named as project team members during your review of the project charter.
Which of the following does this question describe?
A. Resource availability
B. Pre-assignment
C. Staffing management plan
D. Virtual teams
3. 你管理一个内部服务项目并处于计划过程中,你注意到在你审阅项目章程时发现某些员
工已经被指定为项目团队成员。
这个问题说明了:
A. 资源可用性
B. 预分派
C. 人员配备管理计划
D. 虚拟团队
4. The risk management plan accomplishes all of the following except:
A. It defines the methodology to risk management on the project.
B. It describes the risk categories.
C. It defines the roles and responsibilities of the risk management team.
D. It addresses responses to individual risks and how they will be carried out
project.
the
during
4. 风险管理计划进行以下各项,但不包括:
A. 定义项目风险管理的方法论
B. 描述风险类别
C. 定义风险管理团队的角职责
D. 处理单个风险的应对以及在项目中如何实施
5. You are using the interviewing technique of the Perform Quantitative Risk Analysis process.
The probability distribution you intend to use is triangular distribution.
All of the following statements are true regarding this question except:
A. Interviewing techniques are used to quantify the probability and impact of
the risks on project objectives.
B. The information gathered depends on the type of probability distribution
used.
C. The triangular distribution typically uses symmetrical discrete distribution.
D. Triangular distributions rely on relative likelihood to quantify risks.
5. 你在实施风险定量分析过程使用访谈技术,你打算使用的概率分布是三角分布。
下面哪一个说法是错误的?
A. 访谈技术应用于项目目标风险的概率和影响的量化
B. 收集的信息取决于所选用的概率分布类型
C. 三角分布典型的使用对称的非连续性概率分布
D. 三角分布依靠相对概率来量化风险
6. If EV = 114, PV = 120, and AC = 103, what are CPI and SPI, respectively?
A. 1.1 and .95
B. 1.2 and 1.05
C. 1.05 and 1.2
D. .95 and 1.1
6. 如果EV = 114, PV = 120, AC = 103,那么CPI和SPI分别是多少?
A. 1.1 和.95
B. 1.2 和1.05
C. 1.05 和1.2
D. 0.95 和1.1
7. Your company is very excited to work on a major mew project. Although the contract is not
yet signed, your management wants you to go ahead and begin to staff the project.
What should you do?
A. Wait until the last minute to do so
B. Ask the customer for a letter of intent
C. Explain to management that this would not be a good idea at this point
D. Only start to collect resumes and not committee any funds
7. 承担一个重要的新项目使你的公司非常兴奋。尽管合同还没有签订,但你的管理层却让
你往下进行并开始为项目配置人员。
你应该怎么做?
A. 等待,直到最后时刻再这样做
B. 向客户索要一份意向书
C. 向管理层解释在此时这样做不合适
D. 只开始收集个人简历并且不负责任何资金
8. These two processes in the Controlling process group are performed in parallel to assure
correctness and acceptance of the work. Which are they?
A. Perform Quality Assurance and Verify Scope
B. Perform Quality Assurance and Control Scope
C. Perform Quality Control and Verify Scope
D. Perform Quality Control and Control Scope
8. 在控制过程中有两个过程同步进行以保证工作的正确性和验收,这两个过程分别是:
A. 实施质量保证和核实范围
B. 实施质量保证和控制范围
C. 实施质量控制和核实范围
D. 实施质量控制和控制范围
9. All of the following statements are true regarding the time constraints of imposed dates and
key events except:
A. Imposed dates and key events constraints are inputs to integrated change
process.
control
B. Imposed dates apply to activities that must start no later than or finish no
later than a specific date.
C. The key events time constraint applies to the completion of deliverables by
版权声明:本站内容均来自互联网,仅供演示用,请勿用于商业和其他非法用途。如果侵犯了您的权益请与我们联系QQ:729038198,我们将在24小时内删除。